SUB-BULK Water Meter Installation with Chamber Construction
SUB-BULK Water Meter Installation with Chamber Construction

SUB-BULK Water Meter Installation with Chamber Construction

About this project

Preparation for Request for Proposal (RFP) of Project

First Proposal from AHAT

Email Communication for clarification

MB shared The PO on 20-12-2022. The Project Completion Expectation 08 Weeks of PO Project Completion Expet: Feb 14, 2023

Flow Meter MAS & Data Sheet

Materials Approval _ MB

First Email Notice AHAT: Delay Mobili. Due to New Year (January 16, 2023)

MB: Reminder of Delay more than the notice by One & Half Month (Apr 2, 2023): AHAT request another delay to 30th of May 2023

AHAT: informed MB the exact delivery Flowmeter on May 22, 2023

The kick-off meeting took place on May 23, 2023, at the Muscat Bay site.

June 01, 2023: AHAT Email to MB Regarding Unexpected Construction Findings and Necessary Adjustments in Zone-5A

Delivery of Flowmeters & Strainers 6/19/2023

Additional information and documents

Request for Shutdown - Zone-5, Zone-8 Portable water line on July 07, 2023

AHAT Documents

CX-CRM
image
image
image
image
image
image
image
image
image
image
image
image
image
Sub bulk water ahatL2 Flowmeters - SUB-BULK Water Meter With Chambers Installation  ( Z03 A&B), Z05 & Z08 L2 Flowmeters - SUB-BULK Water Meter With Chambers Installation ( Z03 A&B), Z05 & Z08

Media

SUB-BULK Zones Water Meter with Chambers ConstructionSUB-BULK Zones Water Meter with Chambers Construction