Project Steps Tracker
💡

Project Steps Tracker

Status
In progress
Assign
Task
Description
Status
Obtaining Necessary Permits
Secured all local regulatory approvals and environmental clearances required for the Borewell Project.
☑️
Site Selection
Identified the most suitable location for the borewell after an extensive ground survey.
☑️
Soil Testing and Hydrogeological Assessments
Completed comprehensive soil composition and hydrogeological evaluations to ensure suitability for borewell operations.
☑️
Drilling
Reached the required depth for water extraction, employing advanced drilling rigs and adhering to engineering recommendations.
☑️
Water Level Analysis
Analyzed water levels to establish a baseline for continuous monitoring and management.
☑️
Installation of Casing
Installed protective casing to prevent contamination and maintain structural integrity of the borewell.
☑️
Pump Installation
Set up submersible pumps for efficient and reliable water extraction from the borewell.
[ ]
Pump Testing
Conducted tests to ascertain the discharge rate and water quality, ensuring operational excellence.
[ ]
Implementation of Mechanical Works
Executed the setup of mechanical infrastructure required for the borewell functionality, including pumps and control systems.
[ ]
Implementation of Civil Works
Completed essential structural developments, including access roads and borewell housing, to facilitate easy maintenance and operation.
[ ]
Water Tapping Strategies
Devised and executed strategies for tapping water for irrigation, prioritizing sustainability and minimal environmental impact.
[ ]
Final Quality Assurance
Carried out a comprehensive quality check of all borewell components and systems to confirm they adhere to the required standards.
[ ]
Muscat Bay Requires Team Training and Handover to FM Team for Operation & Maintenance
Organized training sessions for stakeholders on managing and maintaining the borewell system. Formally handed over the project to the operational team.
[ ]