SUB-Bulk Watermeter Installation with Chambers Constructions
Title | Column 1 |
---|---|
Description | |
Nursery Building | |
Manunal Excavation | |
Supply and fixing of 1" flow meter, strainer and valve | |
Construction of chamber with PVC box | |
Zone 8- A | |
Manual excavation | |
Construction of chamber with pvc box at top and block work at bottom | |
Remove and refix existing solenoid valve to new chamber | |
Supply and fixing of 2" flow meter | |
Zone 8- A | |
Manual excavation | |
Construction of chamber with pvc box at top and block work at bottom | |
Remove and refix existing solenoid valve to new chamber | |
Supply and fixing of 3" flow meter | |
Near Spar Building | |
Manual Excavation - 175m | |
Supply and install 2" HDPE PN16 line from exiting 4" line to overhead tank | |
Supply and fixing of 2" flow meter, strainer and gate valve and float valve on the tank | |
Asphalt road crossing with exiting sleeve | |
Interlock road crossing with new 3" HPVC sleeve | |
Excavation depth - 50 cm | |
Terms & conditions | |
All permits to be arranged by client | |
Accommodation for the team to be provided by client | |
Hard rock excavation is not considered in the scope | |
Any works which are not mentioned in BOQ shall be considered as variation | |
Payment terms | |
30% advance along with PO | |
Completion | |
15 days from date of PO |