MOM With Project Contractor to Discuss The Below Points - on 24-06-2024
Excavation Permit and Krooki Coordinates:
- Confirm the submission of a clear and accurate Krooki for the excavation permit.
- Determine a timeline for resolution if not already submitted.
Compliance with Stop-Work Order:
- Verify that all work has been halted as per the instructions until approvals are in place.
- Discuss any work done post the issuance of the stop-work order and its implications.
Approval of Mobilization Plan:
- Confirm receipt and review of the updated mobilization plan including the fencing layout.
- Ensure the plan now includes the placement of site offices and guard houses.
Fencing Installation and Site Preparation:
- Approve the final design and layout of the fencing.
- Schedule the installation of the approved fencing and ensure it meets the community and aesthetic requirements.
Signboard Installation:
- Discuss the removal of the temporary signboard deemed unsuitable.
- Review and approve the design for the new, permanent signboard that aligns with Muscat Bay’s image.
Utility Arrangements for Construction:
- Confirm arrangements for water and electricity supply via tankers and their suitability for the site.
- Ensure all utilities setup does not interfere with local services and complies with regulations.
Community Communication and Impact:
- Establish a clear communication plan to inform the community about ongoing and upcoming construction activities.
- Discuss measures to minimize disruption and address community concerns, especially regarding noise and site cleanliness.
Documentation and Approvals:
- Review all submitted documents for compliance with requirements.
- Set deadlines for any pending submissions and discuss the process for expedited review and approval.
Monitoring and Reporting:
- Agree on a regular update schedule and format to monitor the project's progress.
- Discuss the roles and responsibilities in monitoring compliance with the mobilization plan.
- Share the sewage line with Project contractor
- Share also the PO water line and connection
- Sewage line charges